|
Pipeline's Dirty Little
Secrets:
Placer Dome's New Mine in
Crescent Valley experiencing problems
By Christopher Sewall
"This is a fabulous project,"
exclaimed Placer Dome CEO John Wilson at the
July 8th celebration of Cortez Gold’s
(Placer Dome/Kennecott) new Pipeline gold
mine. The celebration was typical of the
uncritical boosterism surrounding the opening
of new mines in Western Shoshone country.
Governor Bob Miller, and former U.S. Rep
Barbara Vucanovich, were on hand to sing the
praises of Nevada’s responsible mining
industry. Yet behind the scenes the Pipeline
project was facing significant problems with
its dewatering operation. This system of pumps
and ponds is supposed to lower the groundwater
table at the mine, and then return the water
to the aquifer, resulting in no loss or
deterioration of groundwater. Unfortunately
the system isn’t working as well as the mine
predicted; all the water isn’t getting back
into the ground and the water that is
returning to the aquifer is contaminated.
The potential for degrading groundwater
quality or quantity in arid Crescent Valley
was one of the significant impacts the BLM
identified during the Pipeline planning
stages. The dewatering system, including
‘reinfiltration ponds, ’ was Placer
Dome’s answer to the voluminous criticism of
the project from local Western Shoshone,
ranchers and environmentalists. Water would be
pumped near the pit and then piped to shallow
ponds several miles away where it would seep
back under the ground. This, the mine claimed,
would result in no groundwater loss and would
help prevent the drying of springs due to the
lowered water table around the pit. The BLM
permitted 126 acres for all the ponds
necessary to dispose of the water for the life
of the mine.
Press coverage of the permitting and
construction of the mine was extensive, yet
little to no mention was made of dewatering
operations when they commenced in August 1996.
Soon after dewatering began Cortez realized
that their ponds were not infiltrating water
at the rate predicted. Rather than informing
the State or the BLM of this rather
significant problem, Cortez moved forward with
expanding mining and dewatering at the
Pipeline Pit. Finally on June 3rd, 1997 Cortez
approached the BLM with an emergency proposal
to remedy their inadequate reinfiltration. The
solution: construct an additional 236 acres of
ponds, above and beyond, those originally
permitted. Cortez claimed it was absolutely
necessary to build these ponds because the
water they couldn’t reinfiltrate was
creating unsafe working conditions in the pit.
As usual the State and the BLM deferred to
the needs of the mining company and approved
the plan in mid-June. This approval was
appealed by two organizations: Great Basin
Minewatch(GBMW), a coalition of environmental
and Native American organizations; and Western
Shoshone Resources Inc. (WSRI), an
organization which works closely with the WSDP
and the Danns. The appeal before the Interior
Board of Land Appeals (IBLA) was not the first
aimed at Cortez. GBMW appealed the original
Pipeline approval in March 1996, one of the
points being that the BLM had inadequately
analyzed the impacts of dewatering. While the
IBLA has yet to rule on this initial appeal,
the current dewatering problems lend credence
to the arguments presented last year.
Since the appeal, problems with the
dewatering facilities have become more
apparent, even after the two additional sets
of ponds were constructed to remedy the
situation. In June, August, September, October
and November 1997 dewatering facilities
overflowed. One set of ponds, the ‘Highway
Infiltration’ site, has developed springs
downhill from it. This results from the water
in the ponds hitting a relatively impermeable
layer, and then flowing downhill to emerge on
the surface. The quality of this water is
quite bad, containing potentially harmful
levels of manganese and antimony.
The groundwater underneath many of these
ponds is little better. Groundwater monitoring
conducted in late September indicated that 13
of 33 monitoring wells had constituents
exceeding drinking water standards. Five more
monitoring wells indicated high levels of
boron, a mineral detrimental to crops if the
water is used for irrigation. Cortez has
responded that these levels are only temporary
as the soils get ‘flushed.’ We can only
hope they are correct.
In addition to the water quality problems,
the reinfilitration ponds are contributing to
other environmental impacts. Evaporation will
be nearly tripled by the new ponds, creating
permanent groundwater loss. Water saturating
the ground around some of the facilities is
drowning native vegetation in some locations
and causing a salt crust to build up on the
surface in others.
State and BLM documents suggest that the
mine is to blame for many of these problems.
Some documents make references to poor
monitoring and a lack of internal
communication while others express the feeling
that Cortez is unable to deal adequately with
the dewatering. The State denied several
requests by Cortez to increase their pumping
rate because the Nevada Division of
Environmental Protection (NDEP) felt they
could not manage any more water. Other
documents suggest that accelerated mining may
have caused the dewatering problems, as Cortez
integrated the development of the South
Pipeline mine expansion. This evidence
supports the contentions of the 1996 and 1997
appeals of GBMW and WSRI that Placer Dome has
intended to expand the Pipeline mine since the
beginning of its permitting process.
Water has always been the primary concern
expressed by the critics of the Pipeline
Project. Cortez and the BLM assured people
throughout the permitting process that
extensive computer modeling had been conducted
and the impacts of the project would be
limited. And while they couldn’t be 100%
sure, they were quite confident in their
calculations. Now we have the actual results
of this ‘experiment’ and it seems as
though those models weren’t as good as we
were lead to believe. The Final Environmental
Impact Statement claimed that the
reinfiltration ponds would return water to the
aquifer at a rate of 4 ft/day. This was a
conservative estimate we were told. Cortez now
has four sets of reinfiltration ponds
operating for the Pipeline project. Only one
set of ponds exceeds an infiltration rate of 2
ft/day. The remaining three facilities absorb
water at less then 2 ft per day, with one of
the original sets of ponds averaging only .96
ft per day. This is a significant
miscalculation.
The problems with computer modeling are
represented in the cliched phrase
"garbage in-garbage out." Models are
based on a series of assumptions. If any of
the assumptions are wrong or miscalculated
they can throw off the entire model.
Cortez’s failure to accurately predict the
reinfiltration capabilities calls into
question their other predictions surrounding
dewatering, including what the water quality
will be like in the pit after mining and how
long it will take the pit to refill. Tom
Myers, a hydrologist working with GBMW, has
recently pointed out that the model used to
estimate the refill of the Pipeline is very
sensitive. Varying certain factors in this
model will cause the predicted refill times to
range from 11 years to over 300 years. Because
the time it takes to refill affects the
quality of the water in the pit, water quality
calculations could be way off.
The continuing difficulties with the
dewatering system at the Pipeline project,
even after additional ponds had been
constructed, finally led the regulatory
agencies to take action. On September 2nd the
Nevada Bureau of Mining Regulation and
Reclamation issued a Finding of Alleged
Violation and Order. The BLM issued a similar
Notice of Non-Compliance on September 11th.
Both required the mine to come up with a more
detailed and effective management plan for the
dewatering facilities. However, since the
notices were issued, several overflows have
occurred, leading one to question the
effectiveness of these regulatory actions and
the agencies implementing them.
Neither the BLM nor the State has been
strong in regulating Pipeline’s faulty
dewatering schemes. The BLM didn’t know
until the end of May 1997 that Cortez would
want more ponds to accomplish its dewatering
program, 9 months after the mine recognized
the lower rates of infiltration. The
environmental problems associated with the
reinfiltration ponds could probably have been
avoided if the BLM had fully evaluated the use
of reinjection wells. These are a series of
pumps which reinject water into the aquifers
it was removed from, eliminating groundwater
loss to evaporation and reducing if not
eliminating water contamination from the
infiltration process. The BLM rejected this as
being too expensive and creating too much
surface disturbance. The second argument rings
hollow after the BLM permitted an additional
236 acres of disturbance for the new ponds.
Current predictions of Pipeline’s cost of
production for 1998 are $100 an ounce, making
it Placer Dome’s most profitable mine, and
certainly calling into question why using
reinjection wells would be financially
unfeasible. Reinfiltration ponds were simply
the cheapest way of getting rid of water that
was in the way, regardless of the impacts.
Rather then requiring a more environmentally
resposible option the BLM let the Pipeline
project pursue the easiest solution.
The State has let Pipeline off quite easily
as well. Despite recent statements that Cortez
will be required to provide some sort of
restitution, perhaps a fine, but more likely a
mandatory public service project. The State
has let them off the hook more times then not.
On May 29th Cortez was informed by the NDEP
that it had violated its permit by
constructing infiltration facilities before
they were approved. Subsequently the NDEP
learned that Cortez had modified the original
infiltration ponds in 1996 by drilling
boreholes in their bottoms to make the water
infiltrate faster. Neither the BLM nor the
State knew about this action until September
1997, when it was revealed in documents filed
in response to the GBMW and WSRI appeals.
Despite this deception, the State seems ready
to forget about this incident.
An examination of the evidence leads one to
see the unfolding Pipeline Project not as a
"fabulous project," but more as a
project out of control. Out of the control of
the Western Shoshone whose land it is built
upon. Out of control of the regulatory
agencies whose supposed oversight is
protecting the public interest. And out of
control of the mine operators themselves, who
overestimated their ability to deal with the
water they need to pump to get the gold. In
this overwhelming desire to grow, Placer Dome
has forgotten an important fact. In a valley
that receives 7.25 inches of precipitation a
year, water is gold, and it’s the only thing
that will grow the most important thing, life.
Main
Page of the Western Shoshone Defense Project
Background
on Western Shoshone issues
|